Reservoir Street Sidewalk: Dutch Mill Court to Harrisonburg Crossing

  • Increase
  • Normal
  • Decrease

Current Size: 80%

The project will construct approximately 1,200 feet of sidewalk on the east side of Reservoir Street from Dutch Mill Court to the Harrisonburg Crossing shopping center entrance to fill gaps in the pedestrian network. The sidewalk will be 5 foot wide with a 2 foot wide grass buffer strip between it and back of curb. The bridge over I-81 in the middle of the corridor has existing sidewalk. The project will make pedestrian improvements to the signalized intersection of Reservoir Street and the Harrisonburg Crossing shopping center entrance. 

Project Schedule:

Preliminary engineering and public engagement – 2025-27

Right-of-way acquisition and utility relocation – 2028-29

Construction – 2029-30