Mountain View Drive Stream Restoration

  • Increase
  • Normal
  • Decrease

Current Size: 80%

This project includes the restoration of approximately 1,730 linear feet of stream along Mountain View Drive. A Preliminary Engineering Report was initiated by City Council and was completed in October 2017.

PDF [11MB] Mountain View Drive Preliminary Engineering Report

The City awarded Ecosystem Services, LLC with the design engineering contract. Gay and Neel, Inc. will perform surveying, utility relocation, and plat development as a subcontractor. 

Ecosystem Services, LLC experience includes: 

  • Murray Run Stream Restoration
  • Blue Leaf Stream Restoration
  • Mossy Creek Water Quality Restoration
  • Edith J. Carrier Arboretum Stream Restoration
  • Ivy Creek Water Quality Restoration Bank

 

Murray Run Before Stream Restoration

Murray Run Before

Murray Run After Stream Restoration

Murray Run After

 

Schedule:

June 2018:  Surveying Complete

November 2018:  30% Design Plans Complete

March 2019:  60% Design Plans Complete

Early April 2019: Community Engagement/Public Meeting

Late June 2019: 100% Design Plans Complete

Late July 2019: All permits acquired

Early August 2019: Go to Bid

November 2019:  Construction Start (opening window)